Metropolitan Water Board v Dick, Kerr & Co [1918]

Facts

  • Contract to build reservoir accounted for possibility of delay
  • Policy caused project to be delayed indefinitely

Issue

  • Was contract frustrated?

Decision

  • Yes

Reasoning

  • Although delay accounted for, permanent delay not