Davis Contractors v Fareham Urban District Council [1956]

Facts

  • Building work took 22 months, rather than 8

Issue

  • Could contract be frustrated?

Decision

  • No

Reasoning

  • Labour shortages caused quality issue, not fundamental to contract as type of performance not altered