Victoria Laundry v Newman Industries [1949]

Facts

  • The defendants were 30 weeks late in delivering new boilers to the claimants
  • This late delivery meant that the claimants could not accept some particularly lucrative Government contracts

Issue

  • Could damages be awarded for loss of profits from the lucrative contracts?

Decision

  • No

Reasoning

  • Damages awarded for ‘normal’ profit loss only as defendants were unaware of lucrative contract loss certainty
  • Hadley v Baxendale [1854] is a two limb test, normal then special tests
RELATED CASE  Re Brocklehurst [1978]

Posted in Contract Law Revision Notes.

This page was last updated on 30th April 2014

© 2020 Webstroke Law - Terms and Privacy Policy